Port of Alaska in Anchorage
Port of Alaska in Anchorage

Test Pile Program Updates Will Be Posted Here

Published: March 18, 2016

The 30-day window for test pile construction is anticipated to begin April 29, 2016. Ten piles will be installed, with each pile taking between 3 and 4 hours to install.

During the TPP, the POA will provide updates at regularly scheduled Government Hill Community Council meetings (http://communitycouncils.org/servlet/content/17.html), as well as updates here on the POA website, and send out weekly updates via e-mail.